Washington Scheduled Network Maintenance [06/13/2009]


Tony

Recommended Posts

Date: Sunday, June 13, 2009 (06/13/2009)

Start time: 03:00 EDT

End time: 04:00 EDT

Duration: 1 hour

Service Affected: WDC01 Public Network

Reason: IOS Upgrade

Device: cer01.wdc01, cer02.wdc01

Location: wdc01

==================================================

Datacenter Engineers will be conducting maintenance on the Customer Edge Routers in Washington, DC. During this time, each one will be upgraded and reloaded. We expect no impact to customers; however, you may notice some higher than normal latency as routes re-converge to redundant CER routers. Each reload should take approximately 15 minutes.

Customers should not expect a service outage as a result of this work.

==================================================

Link to comment
Share on other sites

  • 3 weeks later...
Guest
This topic is now closed to further replies.